Question #3
An agile project has three more iterations before the release. There is a lot of report functionality to be created and defects to be cleared. During a daily scrum, a team member suggests a timebox spike to find a more efficient way to deliver reports. What should the project leader do?
Correct answer: A
Explanation
Self-organizing teams decide how to balance their work; the leader supports rather than directs. Letting the team weigh the spike against the release goal respects their ownership and may improve delivery of the reporting work.
Question #9
Midway through a sprint, a scrum team member advises the team of a new requirement that may change the initial scope. What should the team do?
Correct answer: C
Explanation
The product backlog is the single queue for new requirements, so the team adds the item and lets the product owner prioritize it. Recording it as change-management scope creep ignores the agility the process allows.
Continue with PMI-ACP: PMI Agile Certified Practitioner
Unlock the full question bank
You have read the first 10 questions. A subscription opens every question in PMI-ACP: PMI Agile Certified Practitioner, the full timed practice test, and your progress and weak-topic reporting.
Single exam
$19.99for 30 days
Full question bank and practice test for one exam, for 30 days.
Single exam
$49.99for 1 year
One exam for a full year. Nothing renews and nothing to cancel.
Full access
$39.99/mo
Every exam in the catalogue, month to month.
Full access
$199.99/yr
Every exam in the catalogue for a year.
Already subscribed? Sign in to pick up where you left off.
All PMI-ACP: PMI Agile Certified Practitioner practice questions →