Question #5
Which factor is LEAST important to consider when assessing the eligibility of a contractor?
Correct answer: B
Explanation
Personal connections should not affect the eligibility assessment; objective measures like past performance and financial stability are more important.
Question #8
If a contractor intends to subcontract a portion of the work, what should the contracts manager ensure first?
Correct answer: C
Explanation
The original contract may contain a clause regarding subcontracting that must be adhered to before proceeding.
Continue with CPCM: Certified Professional Contracts Manager
Unlock the full question bank
You have read the first 10 questions. A subscription opens every question in CPCM: Certified Professional Contracts Manager, the full timed practice test, and your progress and weak-topic reporting.
Single exam
$19.99for 30 days
Full question bank and practice test for one exam, for 30 days.
Single exam
$49.99for 1 year
One exam for a full year. Nothing renews and nothing to cancel.
Full access
$39.99/mo
Every exam in the catalogue, month to month.
Full access
$199.99/yr
Every exam in the catalogue for a year.
Already subscribed? Sign in to pick up where you left off.
All CPCM: Certified Professional Contracts Manager practice questions →